6. Development & testing per sprint.

Who: Agile Project Team

Process step description: Agile Project team to work on code and documentation and testers to test functionality as stories are delivered.

...

Meetings: Monthly (1st month -target features and bugs for release and suggest first sprint; 2nd month - suggest targets for second sprint and groom icebox; 3rd month - suggest targets for third sprint and groom icebox; 4th - start preparation for next sprint)

 

...

Project team (code, testing, and documentation contributors):

Task:  Implement features and bug fixes and documentation additions according to prioritization determined by Prioritization team.  Will organize prioritized work into three consecutive month-long sprints.  

...