Completed Feb 16 sprint: 18 stories accepted; 9 stories rejected
Started March 16 sprint: 27 stories target; 11 for container mgmt., 9 for PUI, rest for miscellaneous
Still aiming for April release. Two challenges remain: 1) accommodate more parallel id sequences in the container mgmt. conversion process and 2) ensure conversion process does not convert data already converted
Training:
Workshops at:
Harvard’s Countway Library of Medicine
UC Santa Cruz
Guggenheim Museum Archives
Tri-colleges
Conferences / Presentations:
Code4Arc (preconference to Code4Lib): Brad W. presented an ASpace update remotely; Chris Fitzpatrick attended.
Training:
Code4Lib: Chris Fitzpatrick attended and staffed ASpace table; led a breakout on the ASpace API.
Digital Preservation Management workshop at Emory: Brad attended, gave two presentations and sat on two panel discussions