Fourteen day process, beginning at noon on Friday and concluding at noon on the second Thursday following the start. 

DAY

Planning / Development

Testing

First Friday

Sprint starts

  • Sprint report presented (see below for contents)
  • Process discussed
  • Contents of new sprint identified and discussed

Testing assignments delivered for past sprint

 

 

 

First Friday to Second Thursday a.m.

 

Development of sprint contents

 

 

 

 

First Friday to Second Friday

 

Testing conducted and reported for past sprint

 

 

 

Second Friday

Start scoping of next sprint

  • Work candidates identified
  • Time estimates to be provided

Testing completed

 

 

 

Second Monday-Thursday

Remediation of problems / bugs revealed by testing

 

 

 

 

 

 

 

Second Thursday

Sprint ends

  • Sprint report prepared
    • What was tested
    • What was completed
    • What was deferred until following sprint

 

 

 

 

Following Friday

New sprint starts

 

 

Communciation:

  • Within development / prioritization team via reports, email, etc.
  • IRC channel:  open 24/7
  • Standups:  10:00 – 10:30 a.m. EST Mondays and Wednesdays.  11:00 – noon Fridays is for planning within dev team.  