ArchivesSpace Public user interface development project 2016-2017


 

 




 

Project/Event

PUI development project

Organizer

ArchivesSpace, Harvard, Yale

High-level overview of key work phases and deliverable dates.

  

 

 

 







Project Phase

Starting

Ending

Phase 1

5/23/2016

6/3/2016

Phase 2

5/23/2016

9/6/2016

Phase 3

6/20/2016

8/5/2016

phase 4

9/6/2016

12/9/2016

phase 5

12/16/2016

12/16/2016

phase 6

1/3/2017

2/28/2017

phase 7

3/1/2017

3/31/2017



 

Project Phase

Starting

Ending

Work List & User stories

5/23/2016

6/3/2016

 Development sprints

6/14/2016

9/6/2016

 UX and wac micro testing

6/20/2016

8/5/2016

UX and WAC Macro Testing

9/6/2016

12/13/2016

Candidate Release of PUI

12/16/2016

12/16/2016

Community Testing of PUI

1/3/2017

2/28/2017

PUI 2.0 General release

3/31/2017

3/31/2017

 


May 2016

  • Planning meeting at Harvard

  • Start meetings on defining list of work and polishing user stories

...

  • UX and WCA testing continues

  • Community testing of PUI candidate release (via pui.hudmol.com) commences


December 2016 - March 2017

  • Work completes continues on PUI candidate release


February 2017

  • Technical documentation on configuring PUI completed


January March 2017

  • Community testing of Complete user documentation for PUI

  • Release new PUI candidate release

February 2017

  • Community testing of PUI candidate release continues

  • as part of ArchivesSpace 1.6 release

April - June 2017

  • Incorporate feedback from community into general release planning/remediation

  • Complete user documentation for PUI

...

  • Final preparations on General Release of PUI “2.0”

  • Public announcement of general release of PUI 2.0