ArchivesSpace Public user interface development project 2016-2017
| High-level overview of key work phases and deliverable dates. | ||||
|
|
May 2016
Planning meeting at Harvard
Start meetings on defining list of work and polishing user stories
...
UX and WCA testing continues
Community testing of PUI candidate release (via pui.hudmol.com) commences
December 2016 - March 2017
Work completes continues on PUI candidate release
February 2017
Technical documentation on configuring PUI completed
January March 2017
Community testing of Complete user documentation for PUI
Release new PUI candidate release
February 2017
Community testing of PUI candidate release continues
as part of ArchivesSpace 1.6 release
April - June 2017
Incorporate feedback from community into general release planning/remediation
Complete user documentation for PUI
...
Final preparations on General Release of PUI “2.0”
Public announcement of general release of PUI 2.0